===== PAGE 1 ===== # Tomlin Middle School New Sidewalks 451374-1-52-01
| Work Type | Sidewalk |
| Phase | Construction |
| Limits | Violet Street, N Ritter Street, Mays Street, N Edwards Street, N John Martin Street, W Granfield Avenue and, Waver Street |
| Project Start | Spring 2027 |
| Length | 1.05 miles |
| City | Plant City |
| County | Hillsborough |
| Road | Edwards Street Granfield Avenue John Martin Street Mays Street Ritter Street W Violet Street |
| Construction Cost | $1.6 million |
| Estimated Completion | Summer 2027 |
| Contractor | Leon America Construction |
| Contact Information | |
| Project Information | |
| Maricelle Venegas\n813-975-6204 | |
| Maricelle.Venegas@dot.state.fl.us | |
| Media Contact | |
| Kayla Mejia\n813-975-6060 | |
| Kayla.Mejia@dot.state.fl.us |

| This project will build new sidewalks near Tomlin Middle School along Violet Street, N Ritter Street, Mays Street, N Edwards Street, N John Martin Street, W Granfield Avenue and, Waver Street in Plant City, Hillsborough County. |
| Construction is anticipated to begin Spring 2027. |
| This project is being constructed in conjunction with FPID 451373-1-52-01. For more information on that project, please click here. |