## I-75 at Pine Ridge Road (exit 107) Interchange Improvements 445296-1
| Project Details |
| Work Type | Interchange Construction |
| Phase | Construction |
| Limits | Along Pine Ridge Road from west of I-75 to east of I-75 |
| Project Start | Early 2025 |
| Length | 0.5 miles |
| City | Naples |
| County | Collier |
| Road | I-75 |
| Construction Cost | $27.5 million (Approximate) |
| Estimated Completion | Mid 2027 |
Contact Information
| Contact Information |
| Construction Project Manager |
| Josephine Mak\n(239) 225-1959 |
| Josephine.Mak@dot.state.fl.us |
| Communications Team |
| Michaela Zawodny |
| Michaela.Zawodny@dot.state.fl.us |