===== PAGE 1 =====
# US 41 (21st St/22nd St) Intersection Improvements at Selmon Expressway 445720-1-52-02
| Project Details |
| Work Type | Signal and Pedestrian Improvements |
| Phase | Completed |
| Limits | US 41 (21st/22nd Streets) at Selmon Expressway |
| Project Start | April 3, 2023 |
| City | Tampa |
| County | Hillsborough |
| Road | Highland Avenue SR 685 |
| Construction Cost | $2 million |
| Estimated Completion | Late 2026 |
| Contractor | Traffic Control Devices, Inc. |
| Contact Information |
| Project Information |
| Maricelle Venegas\n813-975-6204 |
| Maricelle.Venegas@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
Map data ©2026 Google
## About
All construction activities associated with this project were completed on Monday, July 27, 2026.
The Florida Department of Transportation's contractor, Traffic Control Devices, Inc., made safety improvements to the intersection of US 41 (21st Street/22nd Street) at Selmon Expressway in Tampa.
Improvements included:
- addition of new traffic signals
- construction of new mid-block pedestrian crosswalks with raised traffic separators and pedestrian refuges
- installation of signage and necessary pavement markings