US 41 (21st St/22nd St) Intersection Improvements at Selmon Expressway 445720-1-52-02

Project Details
Work TypeSignal and Pedestrian Improvements
PhaseCompleted
LimitsUS 41 (21st/22nd Streets) at Selmon Expressway
Project StartApril 3, 2023
CityTampa
CountyHillsborough
RoadHighland Avenue SR 685
Construction Cost$2 million
Estimated CompletionLate 2026
ContractorTraffic Control Devices, Inc.

About

All construction activities associated with this project were completed on Monday, July 27, 2026.

The Florida Department of Transportation's contractor, Traffic Control Devices, Inc., made safety improvements to the intersection of US 41 (21st Street/22nd Street) at Selmon Expressway in Tampa.

Improvements included:

  • addition of new traffic signals
  • construction of new mid-block pedestrian crosswalks with raised traffic separators and pedestrian refuges
  • addition of new traffic signals
  • construction of new mid-block pedestrian crosswalks with raised traffic separators and pedestrian refuges
  • installation of signage and necessary pavement markings

Contact Information

Project Information

Maricelle Venegas 813-975-6204

Maricelle.Venegas@dot.state.fl.us

Media Contact

Kayla Mejia 813-975-6060

Kayla.Mejia@dot.state.fl.us