Tampa Bay Florida Department of Transportation
SR 52 Landscaping Improvements from CR 579A (Prospect Road) to Fort King Road 452434-3-52-01
Project Details
Work TypeLandscape
PhaseCompleted
Limitsfrom CR 579A (Prospect Road) to Fort King Road
Project StartJune 2024
Length2.1 miles
CountyPasco
RoadSR 52
Construction Cost$1.27 million
Estimated CompletionSummer of 2025
ContractorMorelli landscaping, Inc.
About
All construction activities associated with this project were completed on April 4, 2025. The landscaping installed on this project is in an establishment period until Spring 2027.
This project added landscaping along SR 52 (to the east of I-75) from CR 579A (Prospect Road) to Fort King Road in Pasco County.
Contact Information
The landscape design will enhance the existing medians and right of way corridor while utilizing a diverse mix of site appropriate, Florida-friendly plant species that will increase the tree canopy and compliment the roadway aesthetics, while prioritizing public safety.
Project Information
John McShaffrey 813-975-6390 John.McShaffrey@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us