US 19 Corridor Lighting Retrofit from New York Avenue to County Line Road 254677-5-41
| Project Details |
| Work Type | Safety Improvements |
|---|
| Phase | Completed |
|---|
| Limits | from New York Avenue to County Line Road |
|---|
| Project Start | Early 2023 |
|---|
| City | Hudson Spring Hill |
|---|
| County | Hernando Pasco |
|---|
| Road | County Line Road US 19 |
|---|
| Construction Cost | $600,000 |
|---|
| Estimated Completion | Late 2023 |
|---|
| Contractor | Cone & Graham, Inc. |
|---|
As of January 16, 2024, all construction activities associated with this project have been completed.
The Florida Department of Transportation's Design-Build firm, Cone & Graham, Inc., is making roadway lighting improvements to US 19 from New York Avenue to County Line Road in Pasco County.
Safety improvements include installing new light poles and retrofitting existing light poles along US 19. This project is to finish by late 2023.
Contact Information
Project Information
Maddie Pfingsten
727-575-8334
RoadWork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us