| Project Details | |
| Work Type | Bike Lane/Sidewalk |
|---|---|
| Phase | Completed |
| Limits | 7th Ave to Florida Ave |
| Project Start | September 30, 2024 |
| Length | 4.5 miles |
| City | Tampa |
| County | Hillsborough |
| Construction Cost | $5.03 million (combined w/Ola Ave Project) |
| Estimated Completion | Spring 2026 |
| Contractor | Blacktip Services, Inc. |
All construction activities associated with this project were completed on Wednesday, April 15, 2026.
This project restriped the existing roadway by adding sharrows to accommodate an on-street bikeway along Central Avenue from 7th Avenue to Florida Avenue in Tampa.
Improvements:
Contact Information
Project Information Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
This project was constructed in conjunction with the Ola Avenue new bikeway project from 7th Avenue to Florida Avenue (Financial Project Number 440511-5-52-01).