| Project Details |
| Work Type | Repaving |
|---|
| Phase | Completed |
|---|
| Limits | From SR 60 (Chestnut Street) to Mohawk Street |
|---|
| Project Start | September 2019 |
|---|
| Length | 1.6 miles |
|---|
| City | Clearwater |
|---|
| County | Pinellas |
|---|
| Road | Alt US 19 |
|---|
| Construction Cost | $1.6 million |
|---|
| Estimated Completion | Spring 2020 |
|---|
| Contractor | Hubbard Construction Company |
|---|
The Florida Department of Transportation's contractor, Hubbard Construction Company, is repaving Alt. US 19 (Myrtle Avenue) from SR 60 (Chestnut Street) to Mohawk Street in Clearwater.
Construction activities and lane closure are taking place Monday through Friday from 8 a.m. to 5 p.m.
The $1.6 million project is expected to finish spring of 2020.
Contact Information
Project Information
Dan White 727-575-8300
Daniel.white@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us