## Repaving Multiple Locations at SR 688 (Ulmerton Rd) and SR 580 (Main St) 449780-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Limits | SR 688 (Ulmerton Road) at two locations and SR 580 (Main Street) from Countryside Blvd to east of Mueller's Lane |
| Project Start | August 29, 2022 |
| City | Largo Safety Harbor St. Petersburg |
| County | Pinellas |
| Road | SR 580 SR 688 Ulmerton Road |
| Construction Cost | $4.7 million |
| Estimated Completion | Fall 2023 |
| Contractor | Ajax Paving Industries of Florida LLC |
| Contact Information |
| Project Information |
| Maddie Pfingsten 727-575-8334 roadwork@dot.state.fl.us |
| Media Contact |
| Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us |
## About
As of August 9, 2023, all construction activities associated with this project have been completed.
This project will repave portions of Ulmerton Road and Main Street in Pinellas County.
The locations are as follows:
• Ulmerton Road ramps to and from I-275 in St. Petersburg
• Ulmerton Road between US 19 and 49th Street North in Largo
• SR 580 between Countryside Boulevard and Mueller's Lane in Safety Harbor
Construction is underway and is estimated to finish in the fall of 2023.