Forest Ridge Blvd. New Sidewalks from CR 486/Norvell Bryant Hwy to W. Lake Beverly Dr. 439698-1-52-01
| Project Details |
| Work Type | New sidewalks |
| Phase | Completed |
| Limits | from CR\n486/Norvell\nBryant Hwy to\nW. Lake Beverly\nDr. |
| Project Start | November 2, 2021 |
| Length | 1.9 miles |
| County | Citrus |
| Construction Cost | $2.2 million |
| Estimated Completion | Spring 2022 |
| Contractor | Gosalia\nConcrete\nConstructors |
Contact Information
Project Information
Dave Hoover
352-848-2600
David.Hoover@dot.state.fl.us
Media Contact
Kayla Mejia
Kayla.Mejia@dot.state.fl.us
813-975-6060
Map data ©2023
## About
## All work has been completed and the project was final-accepted from the contractor on May 31, 2022
This project added new 5 foot wide sidewalks near Forest Ridge Elementary School at the following locations;
• along the east side of Forest Ridge Blvd. from CR 486 to the Publix Entrance,
• along the west side of Forest Ridge Blvd. from CR486 to Forest Ridge Elementary School,
• along the east side of Forest Ridge Blvd from Forest Ridge Elementary School to Honey Locust Drive,
• along the west side of Forest Ridge Blvd. from Honey Locust Drive to W. Lake Beverly Dr.
• along the west side of Forest Ridge Blvd from Roosevelt Blvd to Central Ridge Library
• along the south side of West Lake Beverly Drive to the Beverly Hills Community Center