# I-75 southbound Interchange Improvement at I-4 428957-1-52-01
| Project Details |
| Work Type | Interchange Improvement |
| Phase | Completed |
| Limits | I-75 Southbound Exit Ramp to I-4 |
| Project Start | September 2018 |
| Length | 2 miles |
| City | Tampa |
| County | Hillsborough |
| Road | I-4 I-75 |
| Construction Cost | $15.5 million |
| Estimated Completion | Spring 2020 |
| Contractor | Prince Contracting, LLC |
| Contact Information |
| Project Information |
| Tyler Matthews | 813-975-3560 |
| Tyler.Matthews@dot.state.fl.us |
| Media Contact |
| John McShaffrey | 813-975-6930 |
| John.McShaffrey@dot.state.fl.us |
Map data ©2020
## About
All work on the project has been completed. The Florida Department of Transportation accepted this project from the contractor on February 7, 2020 -- 80 days ahead of contract time!
This project relocated the exit point to I-4 (Exit 261) almost one mile to the north and created a 1.25 mile two-lane ramp that is separated from the mainline travel lanes by guardrail.
The two-lane ramp extends to the previous area where the ramps split to go east or west on I-4. Each ramp lane feeds directly into the existing ramps onto eastbound and westbound I-4, allowing for traffic to get into the correct ramp lane well before the current decision point where the ramp splits to the two directions of I-4.
These improvements will increase safety and traffic flow for southbound I-75 approaching interstate 4.