# SR 60 (Kennedy Boulevard) Railroad Crossing Replacement at Willow Avenue 416856-2-52-01
| Project Details |
| Work Type | Railroad Crossing Replacement |
| Phase | Completed |
| Limits | at Willow Ave |
| Project Start | July 7, 2024 |
| City | Tampa |
| County | Hillsborough |
| Road | Kennedy Boulevard SR 60 |
| Construction Cost | $388,968 |
| Estimated Completion | Fall 2024 |
| Contractor | Turtle Infrastructure Partners, LLC |
| Contact Information |
| Project Information |
| Maricelle Venegas | 813-975-6204 |
| Maricelle.Venegas@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
## About
## All construction activities associated with this project were completed on Monday, August 26, 2024
*****8 a.m., Friday, July 12, 2024
CSX and FDOT have reopened the intersection of Kennedy Boulevard and Willow Avenue.
The railroad track repair work is now complete. Thanks for your patience and support of this project!
*****
## CSX Railroad Work Closing Kennedy Blvd at Willow Ave Sunday Night
Beginning at 9 p.m., Sunday, July 7, the Florida Department of Transportation will close Kennedy Boulevard (SR 60) at Willow Avenue in Tampa. This intersection closure is necessary for CSX to perform railroad track repair work.
Kennedy Boulevard at Willow Avenue will remain closed for five days, weather permitting.