| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | From east of 50th Street to east of McIntosh Road |
| Project Start | October 1, 2018 |
| Length | 11 miles |
| City | DoverSeffnerTampa |
| County | Hillsborough |
| Road | I-4 |
| Construction Cost | $27.3 million |
| Estimated Completion | Summer 2020 |
| Contractor | Ajax PavingIndustries of Florida LLC |
As of August 27, 2020, this project was accepted by the Florida Department of Transportation as "completed."
This project repaved I-4 between 50th Street and McIntosh Road in Hillsborough County.
The project was combined with design project 430335-1 to be built as a single construction project. This portion of the project lengthened the I-75 ramps going onto eastbound I-4 to allow drivers more time and space to merge into the mainline travel lanes.
Contact Information
Project Information
Tyler Matthews 813-975-3560
Tyler.Matthews@dot.state.fl.us
Media Contact
John McShaffrey 813-975-6930
john.mcshaffrey@dot.state.fl.us