Financial Project Identification (FPID) No.: 448764-1

SAFETY IMPROVEMENTS

U.S. 192 from U.S. 27 to the Orange County Line

Lake County

PROJECT DESCRIPTION

The Florida Department of Transportation (FDOT) is implementing safety improvements on a three-quarter-mile segment of U.S. 192 (State Road (S.R.) 530) from U.S. 27 to the Orange County line. The purpose of the project is to maintain a safe and reliable travel surface.

CONTRACTOR

In addition to resurfacing, planned improvements include:

PROJECT COST $5.8 million

  • Restriping a section of westbound U.S. 192 to provide a dedicated right turn lane into Town Center Boulevard West.
  • Adding crosswalks at the intersection of U.S. 192 and Town Center Boulevard East. This will include updated traffic signals and reconstructed curb ramps as needed to comply with ADA standards.
  • Adding 6-foot-wide sidewalks on the north and south sides of U.S. 192 where none exist.
  • Resurfacing on ramps to U.S. 27.

WHAT TO EXPECT

Atlantic Civil Constructors Corporation

PROJECT START October 2025

ESTIMATED COMPLETION Summer 2026

Motorists should anticipate areas of uneven pavement within the project limits, a common condition during construction when the contractor applies multiple asphalt layers in phases. Temporary lane closures should also be expected throughout the work zone both day and night, as crews require buffer zones to remain protected from oncoming traffic during construction operations.

Single-lane closures within 600 feet of a signalized intersection are not permitted between 3 p.m. and 8 p.m. on westbound U.S. 192, and between 7 a.m. and 5 p.m. on eastbound U.S. 192.

FOR QUESTIONS, CONCERNS, OR PROJECT UPDATES Send a request to:

Double-lane closures are not permitted between 1:30 p.m. and 9 p.m. on westbound U.S. 192, or between 6:30 a.m. and 7 p.m. on eastbound U.S. 192. Double-lane closures within 600 feet of a signalized intersection are not permitted between 8 a.m. and 11 p.m. on westbound U.S. 192, and 6 a.m. and 8:30 p.m. on eastbound U.S. 192.

Joe Callahan Community Outreach Specialist 352-326-7744 joe.callahan@dot.state.fl.us

Roadway conditions are temporary and will improve gradually as the project progresses. While workers are on site, motorists are strongly encouraged to exercise caution and reduce speed to ensure the safety of everyone on the roadway. The project timeline is subject to change and may be adjusted due to inclement weather or other unforeseen circumstances. For the most current project details and lane closure information, please visit FDOT's Central Florida website at www.cflroads.com. Atlantic Civil Constructors Corporation

For more information, scan the QR code above or visit the project website at www.cflroads.com/project/ 448764-1