### SR 580 (Hillsborough Ave) Repaving from Lagoon St. to Sheldon Rd 445824-1-52-01
| Project Details |
| Work Type | Repaving (High Friction Surface Treatment) |
| Phase | Completed |
| Limits | from W. of Lagoon St. to Sheldon Road |
| Project Start | August 31, 2020 |
| Length | .2 miles |
| City | Town 'N' Country |
| County | Hillsborough |
| Road | Hillsborough Avenue SR 580 |
| Construction Cost | $607,103 |
| Estimated Completion | Early 2021 |
| Contractor | Hubbard Construction Company |
| Contact Information |
| Project Information |
| Salem Dhouib | 813-612-3200 |
| Salem.Dhouib@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
Map data ©2021 Google
## About
## FINAL ACCEPTED ON: JANUARY 22, 2021
This repaving project consists of removing the existing top layer of asphalt and replacing it with a high friction surface treatment to improve friction along the eastbound lanes of Hillsborough Avenue.
Crosswalks are also being added to the intersections of Lagoon Street and Sheldon Road.
Construction is expected to finish in early 2021.