| Project Details | |
| Work Type | Arterial Traffic Management System and Intelligent Transportation System Upgrades |
|---|---|
| Phase | Completed |
| Limits | From Veterans Expressway to I-4 |
| Project Start | March 20, 2023 |
| Length | 3.2 miles |
| City | Tampa |
| County | Hillsborough |
| Road | Hillsborough Avenue SR 580 US 92 |
| Construction Cost | $29.2 million |
| Estimated Completion | Fall 2025 |
| Contractor | Highway Safety Device Inc. |
All construction activities associated with this project were completed on Friday, October 3, 2025.
This design build project installed fiber optic communications tools and hardware along Hillsborough Avenue between Veterans Expressway (SR 589) and I-4 to assist with traffic management.