US 41 Repaving from County Line Rd to Bell Lake Rd & SR 54 Repaving from US 41 to east of Knight Rd 441659-1-52-01 & 441658-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Project Start | November 13, 2023 |
| City | Land O' Lakes Lutz |
| County | Pasco |
| Road | Land O' Lakes Boulevard SR 54 US 41 |
| Construction Cost | $13 million |
| Estimated Completion | early 2026 |
| Contractor | Ajax Paving Industries of Florida LLC |
| Contact Information |
| Project Information |
| John McShaffrey | 813-975-6930 |
| john.mcshaffrey@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
Kayla.Mejia@dot.state.fl.us
Map data ©2026
## About
As of January 13, 2026, all construction activities associated with this project have been completed.
Two projects were combined to be built under one construction contract:
- Repaving 3.25 miles on US 41 between County Line Road and Bell Lake Road (project 441659-1-52-01).
- Repaving 0.75 miles on SR 54 between US 41 and Knight Road (project 441658-1-52-01).
The improvements in this project included milling and resurfacing, pavement reconstruction, pavement markings, drainage improvements, pedestrian / bicyclist enhancements, signage, and sidewalk repairs.
## Project Update
Paving on US 41 was completed in May 2025. Milling and paving operations on SR 54 were completed in September 2025.