# I-75 Interchange Improvements at SR 60 and the Selmon Expressway 428953-1-52-01
| Project Details |
| Work Type | Interchange Improvements |
| Phase | Completed |
| Limits | North of Selmon Expressway to south of Broadway Avenue |
| Project Start | September 2018 |
| City | Brandon |
| County | Hillsborough |
| Road | I-75 SR 60 |
| Construction Cost | $52.4 million |
| Estimated Completion | Summer 2022 |
| Contractor | Prince Contracting, LLC |
| Contact Information |
| Project Information |
| Tom Lay | 813-975-3554 |
| Tom.Lay@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
## About
As of February 18, 2022, all construction activities associated with this project are now complete.
This project rebuilt and extended the length of the SR 60 entrance ramps onto northbound I-75 and modified the southbound I-75 exit ramp to the Selmon Expressway (Exit 256) to improve safety and traffic flow on I-75.