I-75 Interchange Improvements at SR 60 and the Selmon Expressway 428953-1-52-01
| Project Details |
| Work Type | Interchange Improvements |
|---|
| Phase | Completed |
|---|
| Limits | North of Selmon Expressway to south of Broadway Avenue |
|---|
| Project Start | September 2018 |
|---|
| City | Brandon |
|---|
| County | Hillsborough |
|---|
| Road | I-75 SR 60 |
|---|
| Construction Cost | $52.4 million |
|---|
| Estimated Completion | Summer 2022 |
|---|
| Contractor | Prince Contracting, LLC |
|---|
As of February 18, 2022, all construction activities associated with this project are now complete.
This project rebuilt and extended the length of the SR 60 entrance ramps onto northbound I-75 and modified the southbound I-75 exit ramp to the Selmon Expressway (Exit 256) to improve safety and traffic flow on I-75.
Other improvements to major interchanges included:
Contact Information