===== PAGE 1 =====
# I-175 Concrete Pavement Repairs from 16th Street S to 4th Street S 445864-1-52-01
| Project Details |
| Work Type | Concrete Pavement Rehabilitation |
| Phase | Completed |
| Limits | from 16th Street S to 4th Street S |
| Project Start | February 27, 2025 |
| Length | 1 mile |
| City | St. Petersburg |
| County | Pinellas |
| Road | I-175 |
| Construction Cost | $5.8 million |
| Estimated Completion | Early 2026 |
| Contractor | Watson Civil Construction, Inc. |
| Contact Information |
| Project Information |
| Maddie Griffin | 727-575-8334 |
| Maddie.Griffin@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
## About
As of March 30, 2026, all construction activities associated with this project have been completed.
This project involves repairing or replacing concrete slabs on I-175 from 16th Street South to 4th Street South in Pinellas County.
The project will also repair a box culvert which runs along this I-175 corridor.
Construction activities are expected to finish during early 2026.