## US 301/US 98 Repaving from Pond Avenue to north of Long Avenue/Pioneer Museum Road 429075-2-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Limits | From Pond Avenue to north of Long Avenue/Pioneer Museum Road |
| Project Start | June 2019 |
| County | Pasco |
| Road | US 301 US 98 |
| Construction Cost | $2.1 million |
| Estimated Completion | Early 2020 |
| Contractor | D.A.B. Constructors, Inc. |
| Contact Information |
| Project Information |
| Cleo Babb | 352-848-2600 |
| Cleo.Babb@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
RIVER ROAD
ESTATES
Map data ©2020 Google
## About
## THIS PROJECT WAS ACCEPTED ON DECEMBER 14, 2019
This project will repave US 301/US 98 between Pond Avenue and Long Avenue/Pioneer Museum Road in Pasco County.
Construction is expected to finish in early 2020.