## SR 54 Repaving from Old Millpond Drive to Little Road 436421-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Limits | From Old Millpond Drive to Little Road |
| Project Start | January 2020 |
| City | New Port Richey |
| County | Pasco |
| Road | SR 54 |
| Construction Cost | $3.2 million |
| Estimated Completion | Summer 2020 |
| Contractor | D.A.B. Constructors, Inc. |
| Contact Information |
| Project Information |
| Richard Frank | 352-848-2600 |
| Richard.Frank@dot.state.fl.us |
| Media Contact |
| John McShaffrey | 813-975-6930 |
| john.mcshaffrey@dot.state.fl.us |
## About
All work has been completed and the project was final-accepted by FDOT as of September 25, 2020.
This project repaved approximately 3.3 miles of SR 54 between Old Millpond Drive and Little Road in Pasco County.
Other improvements included:
- replacing traffic signals at Little Road and Old CR 54 intersections
adding bus pads and sidewalk