Tampa Bay Florida Department of Transportation
SR 583 (56th Street) and SR 50 (Cortez Boulevard) Safety Improvements at Various Locations 452412-1-52-01
Project Details
Work TypeResurfacing, Sidewalk, Traffic Signals, Signing/Pavement Markings, Lighting, and Drainage
PhaseCompleted
Limits56th St at East Lake Mall Entrance and Temple Heights Rd; and Cortez Blvd at Deltona Rd
Project StartJanuary 6, 2025
Length4.6 miles
CitySpring Hill Tampa
CountyHernando Hillsborough
Road56th Street Cortez Boulevard
Construction Cost$654,321
Estimated CompletionSpring 2025
ContractorBlacktip Services, Inc.
Contact Information
Project Information Maricelle Venegas (Hillsborough) and John McShaffrey (Hernando) 813-975-6204 and 813-975-6930 Roadwork@dot.state.fl.us
Media Contact Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
About
All construction activities associated with this project were completed on April 28, 2025.
This project made safety improvements by installing crosswalks at three separate intersections in Hillsborough and Hernando counties.
Improvements took place at the following locations:
SR 583 (56th Street) at the entrance to East Lake Mall (Net Park) in Tampa
(SR 583 (56th Street) at Temple Heights Road in Tampa
SR 50 (Cortez Boulevard) at Deltona Boulevard in Spring Hill
As part of the improvements the following construction activities occurred as part of this project:
Installed pedestrian signals
Installed crosswalk striping and ADA compliant ramps
Reconfigured median
Installed highway lighting
Replaced pavement markings.