| Project Details | |
| Work Type | Drainage Improvements |
|---|---|
| Phase | Completed |
| Limits | from Walsingham Road to Park Boulevard |
| Project Start | November 2019 |
| City | Indian Rocks Beach Indian Shores |
| County | Pinellas |
| Road | Gulf Boulevard SR 699 |
| Construction Cost | $11.9 million |
| Estimated Completion | Fall 2021 |
| Contractor | Ajax Paving Industries of Florida, LLC |
Contact Information
Project Information
Dan White 727-575-8300
Daniel.White@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
As of January 26, 2022, all work associated with this project has been completed.
This project is improving drainage on SR 699 (Gulf Blvd) between Walsingham Road and Park Boulevard in Indian Rocks Beach and in the Town of Indian Shores in Pinellas County.
Construction activities began at the north end of the project, and it is progressing towards the south. Crews are working Monday through Friday from 8 a.m. to 8 p.m.
Access to businesses and residents are being maintained.
Motorists should anticipate heavier than normal volumes of traffic on Gulf Boulevard during scheduled lane closures.
The $11.9 million project is expected to finish in the fall of 2021.
As of January 26, 2022 all work associated with this project has been completed.