Alt US 19/SR 595 Repaving from Long Bayou Bridge to Hoover Boulevard/95th Street N. 443806-1-52-01

Project Details
Work TypeRepaving
PhaseCompleted
Limitsfrom north of Long Bayou Bridge to Hoover Blvd/95th St. N.
Project StartFebruary 6, 2024
Length.3 miles
CitySt. Petersburg
CountyPinellas
RoadAlt US 19 Bay Pines Boulevard SR 595
Construction Cost$1.2 million
Estimated CompletionLate 2024
ContractorHubbard Construction Company

About

As of May 13, 2024, all construction activities associated with this project have been completed.

This project will repave Bay Pines Boulevard between the north end of the Long Bayou Bridge and Hoover Boulevard /95th Street N.

Construction is underway and expected to be complete in late 2024.