| Project Details |
| Work Type | Repaving |
|---|
| Phase | Completed |
|---|
| Limits | from CurlewRoad and St.Petersburg Drive |
|---|
| Project Start | August 2020 |
|---|
| Length | 2.5 miles |
|---|
| City | Oldsmar |
|---|
| County | Pinellas |
|---|
| Road | SR 580SR 584Tampa Road |
|---|
| Construction Cost | $4,564,699 |
|---|
| Estimated Completion | Spring 2021 |
|---|
| Contractor | HubbardConstructionCompany |
|---|
This project repaved Tampa Road between Curlew Road and St. Petersburg Drive in Oldsmar.
Additional improvements included: minor signalization, sidewalk, and drainage upgrades.