===== PAGE 1 ===== ## Alt US 19 (Seminole Boulevard) Repaving from 53rd Avenue N to 101st Avenue N 436485-1-52-01
Project Details
Work TypeRepaving
PhaseCompleted
LimitsFrom 53rd Avenue North to 101st Avenue North
Project StartMarch 2020
Length3.1 miles
CitySeminole
CountyPinellas
RoadAlt US 19 Seminole Boulevard
Construction Cost$6.8 million
Estimated CompletionSpring 2021
ContractorPreferred Materials, Inc.
Contact Information
Project Information
Sarah Gansz727-575-8300
Sarah.Gansz@dot.state.fl.us
Media Contact
Kayla Mejia813-975-6060
Kayla.Mejia@dot.state.fl.us
Image
Google Map data ©2021 INEGI ## About ## FINAL ACCEPTED ON MARCH 12, 2021 This project will repave Alt. US 19 (Seminole Boulevard) from south of 53rd Avenue N to north of 101st Avenue N. in Seminole. Construction is anticipated to finish in the spring of 2021.