Tampa Bay Florida Department of Transportation
I-75/I-275 Collector-Distributor Roadway from SR 56 to south of County Line Road 430573-2, 430573-3
Project Details
Work TypeNew Road Construction
PhaseDesign
LimitsFrom south of County Line Road to SR 56
Length3.9 miles
CityWesley Chapel
CountyHillsborough Pasco
RoadI-275 I-75 SR 56
Contact Information
Design Manager
Dinyar Sharifabad
975-6172
Dinyar.Sharifabad@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
About
This project will construct a 3-lane southbound Collector-Distributor (CD) road system from the SR 56 southbound on-ramp to the I-75 / I-275 apex to complement the northbound CD road system in Wesley Chapel.
This includes:
A new 2-lane southbound on-ramp from the CD roadway to southbound I-75, which will require widening the bridge over Cypress Creek.
A new bridge over Cypress Creek for the southbound CD roadway
A new fork of I-75 / I-275 southbound
A new bridge for southbound I-275 over the CD road ramp to southbound I-75
New concrete barrier wall separation between the southbound I-75 mainline lanes and the proposed southbound CD roadway.
A proposed ramp from the southbound CD roadway to southbound I-75.
The project is currently in the design phase and has been combined with FPN 430573-3.
Construction is not currently funded.