===== PAGE 1 =====
SR 60 (Brandon Blvd/Hopewell Rd) Repaving from Valrico Road to Turkey Creek Road
440251-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Limits | from Valrico Road to Turkey Creek Road |
| Project Start | April 18, 2022 |
| Length | 4.9 miles |
| City | Brandon Hopewell Valrico |
| County | Hillsborough |
| Road | Brandon Boulevard SR 60 |
| Construction Cost | $6.5 million |
| Estimated Completion | Early 2023 |
| Contractor | Preferred Materials, Inc. |
| Contact Information |
| Project Information |
| Maricelle Venegas | 813-975-6204 roadwork@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 Kayla.Mejia@dot.state.fl.us |
Google's den Rd
## About
Map data ©2023
All construction activities with this project were completed on Friday, February 24, 2023.
This project repaved SR 60 (Brandon Boulevard/Hopewell Road) between Valrico Road and Turkey Creek Road in eastern Hillsborough County.
Construction activities took place during the daytime and nighttime hours. Work required lane closures to occur nightly between 9:30 p.m. and 6 a.m.