STREET IMPROVEMENT
CONSTRUCTION NOTES
- Construct 3" minimum thick A.C. pavement on 4" minimum thick crushed aggregate base. (See General Notes 7 & 8).
- Construct minimum 4" thick A.C. pavement on 6" minimum crushed aggregate base (See Gen. Notes 7 & 8).
- Construct 8" curb and gutter per A.P.W.A. Std. Plan 120 - 1, A2 - 200(8) (See Gen. Note 13).
- Construct 6" curb and Gutter per A.P.W.A. Std Plan 120-1, A2-150(6)(See Gen. Note 13).
- Construct 4" P.C.C. sidewalk. (See Gen. Notes 14, 15 & 16).
- Construct concrete crossgutter per A.P.W.A. Standard Plan 122-1.
- Construct modified concrete wheelchair ramp per City of Palmdale Standard No. C-7, Case ___.(See Gen. Note 14).
- Sawcut and remove 1' minimum existing AC pavement to provide for a neat joint.
- Cold plane 1" to meet centerline and overlay.
- Existing utility equipment (power poles, water meters, fire hydrants, etc.) will be relocated per City Standards and utility company requirements.
- Construct 2" x 6" redwood header, or construct an additional 1' of AC pavement at edge of AC paving.
- Install ___, Type I guide markers per L.A.C.R.D. Standard Plan 84-01.
** Additional project specific Construction Notes to be developed by the design engineer as necessary.
IV - 15