- DETENTION/RETENTION BASIN NOTES (continued)
- Slopes within the basin and slopes outside the landscape maintenance assessment district may be as steep as 2:1 at the discretion of the City Engineer.
- Pipe shall be encased per STD Plan D-6.
- Trench backfill (including irrigation line trenches) shall be compacted to 90% relative compaction and certified by the soils engineer. Alternatively, trenches may be backfilled with a sand-cement slurry (2 sack mix) or Portland Cement Concrete, upon the recommendation of the geotechnical consultant. Inspection of this operation by the geotechnical consultant and the city inspector is required.
- Soils engineer shall verify and approve trench bottom soil prior to placement of pipe.
- C.OUTLET STRUCTURES
- The drain pipe encasement shall be placed on a firm foundation approved by the soils engineer.
- Anti-seep collars are required at 15' intervals for pipe under the embankment, with a minimum of one required in addition to the inlet and outlet erosion protection.
- Discharge shall be to a paved street, channel, or an approved drainage course with grouted riprap. Ripap shall be 12" minimum size rock. Ripap shall be embedded in a minimum 6" into grout.
- The drain pipe shall be a minimum of 15" in diameter and shall be constructed with water tight joints.
- All concrete shall be Portland Cement Concrete 420-C-2000 unless otherwise specified.
- CITY OF PALMDALE...
BASIN NOTES Std. No.
Approved City Engineer Date D-7.2