Final air test has been completed and approved.
When the above work is complete, the Developer shall arrange for the television inspection.
The Developer of the project will notify the City in writing as to the scheduled date of the television inspection.
The entire job will be initially televised and video taped. The tapes and reports shall be delivered to the City.
The Developer will be notified in writing of any deficiencies revealed by the television inspection that will require repair. If corrective work is indicated and Developer wishes to view videotapes, he shall contact the City to set a time for viewing with the Engineer.
Corrective work shall be done. The cost shall be borne by the Developer.
Those portions of the pipeline system that have been corrected must be re-televised and video taped and the tapes and reports delivered to the City.
The procedure outlined in conditions 1 through 7 above will be repeated until all deficiencies observed by television have been corrected to the complete satisfaction of the City.
All video tapes and reports become the property of the City to be used as "As Builts" for future reference.
B. SUBMITTAL REQUIREMENTS
Sanitary Sewer plans shall be submitted as a part of the Street Improvement plan submittal package. (See Page IV-4)
See Page VII-3 for plan checking and submittal requirements.