US 19 / 98 Median Opening at Veterans Drive 405600-2-52-78
| Project Details |
| Work Type | Median |
| Phase | Construction |
| Project Start | September 21, 2026 |
| City | Crystal River |
| County | Citrus |
| Road | US 19US 98 |
| Construction Cost | $405,777 |
| Estimated Completion | late 2026 |
| Contractor | Turtle Infrastructure Partners, LLC |
| Contact Information |
| Project Information |
| John McShaffrey\n813-975-6930 | john.mcshaffrey@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 | Kayla.Mejia@dot.state.fl.us |
| |
Map data ©2026
## About
The improvements under this contract consist of building a median opening on US 19 / US 98 at W Veterans Drive.
The median opening will allow eastbound W Veterans Drive to access northbound US 19 / US 98. An acceleration lane will also be built adjacent to the northbound US 19 / US 98 travel lanes for traffic merging from W Veterans Drive.
Construction began on September 21, 2026.