Tampa Bay Florida Department of Transportation
US 41 Repaving from Hillsborough/Manatee County Line to south of John Sherman Way 456059-1-52-01
Project Details
Work TypeRepaving
PhaseCompleted
Limitsfrom Hillsborough/Manatee County Line to south of John Sherman Way
Project StartNovember 5, 2026
Length3 miles
CityRuskin
CountyHillsborough
RoadSR 45 US 41
Construction Cost$932,163.00
Estimated CompletionSpring 2026
ContractorAjax Paving Industries of Florida, LLC
About
All construction activities associated with this project were completed on Monday, April 2026.
This project repaved US 41 from Hillsborough/Manatee County Line to south of John Sherman Way in Hillsborough County.
Construction activities were expected to finish during spring 2026.
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us