| Project Details | |
| Work Type | Repaving, Safety Improvements |
|---|---|
| Phase | Design |
| Limits | US 92 from Eureka Springs Road to Thonotosassa Road |
| Length | 12.5 Miles |
| City | Dover Mango Plant City Seffner |
| County | Hillsborough |
| Road | Baker Street Hillsborough Avenue US 92 |
This project will repave over 12 miles of asphalt pavement along US 92 in Hillsborough County.
Guardrail installation and replacement, sidewalk improvements, signing and pavement markings, signalization, lighting, ITS, and miscellaneous structures are also included as part of this project.
The project is currently in the design phase. Construction is anticipated to begin in Spring 2027.
Contact Information
Design Manager Jason Jordan 813-975-6169 Jason.Jordan@dot.state.fl.us
Media Contact Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us