| Project Details | |
| Work Type | Arterial Traffic Management and New Highway Lighting |
|---|---|
| Phase | Completed |
| Limits | from Gunn Highway to Bruce B. Downs Blvd. |
| Project Start | February 2023 |
| City | Land O' Lakes Lutz Odessa Wesley Chapel |
| County | Pasco |
| Road | SR 54 SR 56 |
| Construction Cost | $7 million |
| Estimated Completion | Early 2025 |
| Contractor | TransCore ITS, LLC |
Construction is complete on this design-build project which added traffic signal controller upgrades along the SR 54/56 corridor including cameras, fiber optics, and other detection components between Gunn Highway in Odessa and Bruce B. Downs Boulevard in Wesley Chapel.
New highway lighting was also added at these two intersections: Crossings Boulevard and Oakstead Boulevard.
Contact Information
Project Information
John McShaffrey 813-975-6930 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us