===== PAGE 1 ===== Financial Project ID: 439434-1-52-01 & 439434-1-52-02 CONSTRUCTION PROJECT The Florida Department of Transportation will begin work on March 9, 2021 to make improvements to US 27 from Cloverleaf Road to SR 66 in Highlands County. The project length is approximately six miles. The project limits are identified below on the project location map. ## PROJECT IMPROVEMENTS Resurface US 27 from Cloverleaf Road to SR 66 Modify median openings Add left turn lanes at Lake Josephine RV Resort and Heartland Animal Hospital Install curb and gutter, signage and pavement markers Replace guardrail Improve drainage Install new traffic signals at Twitty Road and Lake Josephine Drive Estimated construction cost is $10 million