## US 92 (S Dale Mabry Hwy) Repaving from Ballast Point Boulevard to Sevilla Street 443781-1-52-01
| Project Details |
| Work Type | Resurfacing |
| Phase | Completed |
| Limits | from north of Ballast Point to south of Sevilla St |
| Project Start | August 18, 2025 |
| Length | 1.55 Miles |
| City | Tampa |
| County | Hillsborough |
| Road | Dale Mabry Highway US 92 |
| Construction Cost | $6.5 million |
| Estimated Completion | Summer 2026 |
| Contractor | Ajax Paving Industries of Florida, LLC |
| Contact Information |
| Project Information |
| Maricelle Venegas\n813-975-6204 |
| Maricelle.Venegas@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
Map data ©2026 Google
## About
All construction activities associated with this project were completed on Thursday, May 28, 2026.
This project repaved South Dale Mabry Highway (US 92) from north of Ballast Point Boulevard to south of Sevilla Street in South Tampa.
Other improvements included:
• installed a directional raised median at Kensington Avenue
• installed a raised traffic separator along the left turn lane onto El Prado Boulevard
• installed a raised traffic separator along the median between Fair Oaks Avenue and Lawn Avenue