# I-75 Intelligent Transportation System from Manatee County Line to Big Bend Road 434025-1-52-01
| Project Details |
| Work Type | Intelligent Transportation System |
| Phase | Completed |
| Limits | From Manatee County Line to Big Bend Road |
| Project Start | November 2018 |
| Length | 11.5 |
| City | Apollo Beach Riverview Ruskin Sun City Center |
| County | Hillsborough |
| Road | I-75 |
| Construction Cost | $5,832,000 |
| Estimated Completion | Early 2020 |
| Contractor | Highway Safety Devices, Inc. |
| Contact Information |
| Project Information |
| Shiva Moonian | 813-612-3200 |
| Shiva.Moonian@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
Map data ©2020 Google, INEGI
## About
## FINAL ACCEPTANCE: FEBRUARY 19, 2020
This design-build project will install Intelligent Transportation System components along I-75 from the Manatee County Line north to Big Bend Road including fiber optic cable, closed-circuit television cameras, and Microwave Vehicle Detection units.
An Intelligent Transportation System, or ITS, uses a variety of devices including electronic roadway signs, (called dynamic message signs) and closed-circuit television cameras to monitor roadway congestion, lane closures, and current weather or emergency conditions and advise motorists of travel times.
Construction is anticipated to finish in early 2020.