| Project Details |
| Work Type | Bridge Replacement (2) |
|---|
| Phase | Completed |
|---|
| Limits | from I-275 to 119th Ave |
|---|
| Project Start | January 10, 2022 |
|---|
| City | St. Petersburg |
|---|
| County | Pinellas |
|---|
| Road | 4th Street I-275 SR 687 |
|---|
| Construction Cost | $9 million |
|---|
| Estimated Completion | Spring 2024 |
|---|
| Contractor | Superior Construction Company Southeast, LLC |
|---|
Contact Information
Project Information
Maddie Pfingsten 727-575-8334 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
As of November 15, 2023, all construction activities associated with this project have been completed.
This project is replacing the 4th Street bridges between I-275 and 119th Ave in Pinellas County.
The new bridges will include two twelve-foot travel lanes a six-foot inside shoulder and a ten-foot outside shoulder.
One of the bridges will also include a twelve-foot multi-use path separated by a barrier wall.
Construction is anticipated to finish spring 2024.