===== PAGE 1 ===== # CR 580 (Sam Allen Rd) Widening from SR 39A (Paul Buchman Highway) to Park Road 257862-3-52-01
Project Details
Work TypeWidening
PhaseCompleted
LimitsFrom west of SR 39A (Paul Buchman Highway) to east of Park Road
Project StartNovember 2018
Length2 miles
CityPlant City
CountyHillsborough
RoadPaul Buchman HighwaySam Allen RoadSR 39A
Construction Cost$23.2 million
Estimated CompletionSummer 2022
ContractorC.W. Roberts Contracting, Inc.
Contact Information
Project Information
Melissa Chin813-975-3573
Melissa.Chin@dot.state.fl.us
Media Contact
Kayla Mejia813-975-6060
Kayla.Mejia@dot.state.fl.us
Image
Map data ©2022 ## About All construction activities associated with this project were completed on Thursday, June 30, 2022. ## CONSTRUCTION UPDATE C.W. Roberts Contracting, Inc. was awarded the completion contract to complete the project. The new contractor began work on September 27, 2021, and is expected to finish in the summer of 2022. Why did work stop? On July 28, 2021, the original project contractor notified the Florida Department of Transportation (FDOT) that it was stopping work on the project. On August 3, 2021, FDOT declared the contractor in default. The FDOT projects have contract bonds issued by a surety company, which is a contractual requirement. The surety company was required to obtain a completion contractor; this process has been completed.