===== PAGE 1 =====
## I-75 Interchange Improvement at CR 54 455991-1-52-01
| Project Details |
| Work Type | Interchange Improvements |
| Phase | Construction |
| Limits | Southbound I-75 Exit 279 ramp to CR 54 |
| Project Start | October 5, 2026 |
| City | Wesley Chapel |
| County | Pasco |
| Road | I-75 |
| Construction Cost | $1.7 million |
| Estimated Completion | Spring 2027 |
| Contractor | Blacktip Services Incorporated |
| Contact Information |
| Project Information |
| John McShaffrey\n813-975-6930 | john.mcshaffrey@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 | Kayla.Mejia@dot.state.fl.us |
## About
This project will widen and resurface the existing I-75 southbound exit ramp travel lanes and shoulders to provide dual left-turn lanes from southbound I-75 to eastbound CR 54. Additional improvements include signing and pavement markings, signalization, drainage improvements, and upgraded intersection lighting.