# US 19 Median Barrier Wall Extension from 126th Ave to 66th St and from Whitney Rd to Seville Blvd 445410-1-52-01
| Project Details |
| Work Type | Safety Improvements |
| Phase | Completed |
| Limits | from 126th Ave\nN to 66th St and\nfrom Whitney Rd\nto Seville Blvd |
| Project Start | Fall 2020 |
| City | Clearwater\nLargo\nPinellas Park |
| County | Pinellas |
| Road | US 19 |
| Construction Cost | $1.1 million |
| Estimated Completion | Summer 2021 |
| Contractor | Gosalia Concrete\nConstructors, Inc. |
| Contact Information |
| Project Information |
| David Gillett |
| 727-575-8300 |
| David.Gillett@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
Google®indian Shore
## About
## FINAL ACCEPTED ON WEDNESDAY, FEBRUARY 3, 2021
This project will increase the height of the US 19 median barrier wall at multiple locations in Pinellas County.
Construction is anticipated to begin in the fall of 2020 and be complete in the summer of 2021.