===== PAGE 1 ===== ## Withlacoochee Trail - Repaving Citrus County section 443358-1-52-01
Project Details
Work TypeRepaving
PhaseCompleted
Limitsfrom the Hernando County line to the Marion County line
Project StartOctober 2020
Length29 miles
CityCitrus Springs Inverness
CountyCitrus
Construction Cost$1 million
Estimated CompletionSummer 2021
ContractorAjax Paving Industries of Florida, LLC
Contact Information
Project Information
Austin Petersen352-848-2653
austin.petersen@dot.state.fl.us
Media Contact
John McShaffrey813-975-6930
john.mcshaffrey@dot.state.fl.us
GoogleAbout
The project was accepted from the contractor as completed on June 17, 2021.
This design build project repaved portions of the Withlacoochee Trail in Citrus County. There were sections of the 29 miles of the trail in Citrus County that were rebuilt due to the condition of the existing pavement. Mid-block crossing enhancements were also completed at CR 48 (Orange Avenue) in Floral City.
Design began in October 2020 and construction began in January 2021.
Image