ROADWAY RESURFACING

Pineda Causeway (S.R. 404) from U.S. 1 (S.R. 5) to S.R. A1A

Brevard County

Financial Project Identification (FPID) No.: 448785-1

PROJECT DESCRIPTION

The Florida Department of Transportation (FDOT) is resurfacing Pineda Causeway (State Road (S.R.)) 404) from U.S. 1 (S.R. 5) to S.R. A1A in South Patrick Shores, and the towns of Merritt Island and Palm Shores. The project limits include repaving the interchange ramps at U.S. 1, South Tropical Trail (County Road (C.R.))3), and South Patrick Drive (S.R. 513).

The project also includes several operational enhancements, such as reconstructing the existing traffic signal at the intersection of Pineda Causeway and S.R. A1A with new mast-arm poles.

Additional improvements include installing wrong-way detection systems on ramps that currently lack them, adding bike lanes adjacent to the right-turn lane on Pineda Causeway at the S.R. A1A intersection, and updating the pavement markings.

WHAT TO EXPECT

During construction, motorists should expect intermittent nighttime single-lane closures between 7 p.m. and 7 a.m. Ramp closures may occur between 10 p.m. and 5 a.m. Motorists are advised to proceed with caution when traversing the corridor.

Electronic message boards and other signage will direct traffic through the work zone. The level of work activity and noise may vary during different construction phases. Uneven pavement is a common condition during resurfacing projects, as different layers of asphalt are applied in phases. Motorists are encouraged to remain alert and drive carefully while traveling through the work zone. Road conditions during construction are temporary and will improve as the project advances.

Please note that the construction schedule is subject to change due to inclement weather or other unforeseen conditions. For the most current project details and lane closure information, please visit FDOT's Central Florida website at www.cflroads.com. CONTRACTOR Masci General Contractors, Inc.

CONTRACTOR Masci General Contractors, Inc.

PROJECT COST $10.7 million

PROJECT START September 2025

ESTIMATED COMPLETION Fall 2026

FOR QUESTIONS, CONCERNS, OR PROJECT UPDATES Send a request to:

Ashley Ingham Community Outreach Specialist 321-634-6111 Ashley.Ingham@dot.state.fl.us

For more information, scan the QR code above or visit the project website at www.cflroads.com/project/ 448785-1

SEE REVERSE SIDE FOR PROJECT LOCATION MAP

Follow us on social media