## Ola Avenue New Bikeway from 7th Avenue to Florida Avenue 440511-5-52-01
| Project Details |
| Work Type | New Bikeway |
| Phase | Completed |
| Limits | from 7th Ave to Florida Ave |
| Project Start | September 30, 2024 |
| Length | 4.1 miles |
| City | Tampa |
| County | Hillsborough |
| Construction Cost | $5.03 million (combined w/Central Ave Project) |
| Estimated Completion | Spring 2026 |
| Contractor | Blacktip Services, Inc. |
| Contact Information |
| Project Information |
| Maricelle Venegas | 813-975-6204 |
| Maricelle.Venegas@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
Google WESTSHORE
Map data ©2026 Google
## About
All construction activities associated with this project were completed on Wednesday, April 15, 2026.
This project restriped approximately 4.2 miles of roadway by adding sharrows to accommodate an on-street bikeway with signage along Ola Avenue from 7th Avenue to Kirby Street in Tampa.
Other improvements:
• added speed cushions for traffic calming on Ola Avenue to the south of Osborne Avenue
• created four-way stop intersections at Ola Avenue and Osborne Avenue, and at Highland Avenue and W. Lambright Street
- upgraded curb ramps, added marked crosswalks, and intersection lighting at Columbus Drive (rectangular rapid flashing beacons), SR 574 /MLK (traffic signal), Slight Avenue (pedestrian hybrid beacon)
This project was constructed in conjunction with the Central Avenue new bikeway project from 7th Avenue to Florida Avenue (Project Number 440511-6-52-01).