# SR 687 (4th Street N) Repaving from 106th Avenue N to 119th Avenue N 456060-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Limits | SR 687 (4th Street N) from 106th Avenue N to 119th Avenue N |
| Project Start | February 24, 2026 |
| Length | 1 mile |
| City | St. Petersburg |
| County | Pinellas |
| Road | 4th Street SR 687 |
| Construction Cost | $1.4 million |
| Estimated Completion | Summer 2026 |
| Contractor | Preferred Materials, Inc. |
| Contact Information |
| Project Information |
| Maddie Griffin | 727-575-8334 |
| Maddie.Griffin@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
Publix Super Market Google Gateway Crossing
Map data ©2026 Google
## About
As of July 28, 2026, all construction activities associated with this project have been completed.
The purpose of this project is to preserve and extend the life of the existing pavement through resurfacing along this section of SR 687 (4th Street N) in Pinellas County
Construction is underway and expected to be complete in the summer of 2026.