## I-4 Eastbound Auxiliary Lane from 15th Street to 26th Street 445057-2-52-01
Project Details
| Project Details |
| Work Type | Widening |
| Phase | Construction |
| Limits | 15th Street to 26th Street |
| Project Start | October 16, 2026 |
| Length | 0.7 miles |
| City | Tampa |
| County | Hillsborough |
| Road | I-4 |
| Construction Cost | $10.7 million |
| Estimated Completion | Late 2027 |
| Contractor | Webber, LLC |
| Contact Information |
| Project Information |
| Maricelle Venegas\n813-975-6204 |
| Maricelle.Venegas@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
| About |
| This project is adding one auxiliary lane in the eastbound direction on I-4 from 15th Street to west of 26th Street in Hillsborough County.\nOther improvements include:\n• widening the I-4 eastbound bridge over 21st/22nd Street\n• constructing retaining walls\n• installing new LED lighting\n• adding signing and pavement markings\n• and installing Intelligent Transportation Systems (ITS) |