Tampa Bay Florida Department of Transportation
US 301 (Gall Blvd) Repaving from Hillsborough County line to SR 39 (Paul Buchman Hwy) 440063-1-52-01
Project Details
Work TypeRepaving
PhaseCompleted
LimitsFrom the Hillsborough County line to south of SR 39 (Paul Buchman Hwy)
Project StartOctober 2, 2023
Length3.8 miles
CityZephyrhills
CountyPasco
RoadGall Boulevard Paul Buchman Highway US 301
Construction Cost$6.75 million
Estimated CompletionDecember 4, 2024
ContractorBurgess Civil, LLC
Contact Information
Project Information
John McShaffrey 813-975-6930 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
About
As of December 4, 2024, all work was completed and this project was final-accepted from the contractor.
This project repaved US 301 in Pasco County from the Hillsborough County line to just south of SR 39 (Paul Buchman Highway).
Other project work included curb and gutter, sidewalk, signing, pavement markings, lighting, pedestrian and vehicle signal upgrades, and drainage improvements.
Street lighting was installed at the US 301 / Chancey Road intersection and at the merge of US 301 and SR 39 (Paul Buchman Hwy).