Tampa Bay Florida Department of Transportation
SR 597 (Dale Mabry Highway) Lighting Improvements at Various Intersections 254677-5-20
Project Details
Work TypeLighting Improvements
PhaseCompleted
Project StartJune 21, 2021
CityTampa
CountyHillsborough
RoadDale Mabry Highway SR 597
Construction Cost$391,349.45
Estimated CompletionSummer 2022
ContractorCone & Graham, Inc.
About
As of June 16, 2022, all construction activities associated with this project have been completed.
This design-build project will address safety improvements with the new construction and retrofitting roadway lighting with LED luminaires at various intersections along SR 597 (Dale Mabry Highway) in Hillsborough County.
Various Intersections include:
Contact Information
Project Information
Randy Aebersold 727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
Location 1: SR 597 (Dale Mabry Highway) at Lambright Street
Location 2: SR 597 (Dale Mabry Highway) at Hamilton Avenue
Location 3: SR 597 (Dale Mabry Highway) at Linebaugh Avenue
Location 4: SR 597 (Dale Mabry Highway) at Lake Carroll Way
Location 5: SR 597 (Dale Mabry Highway) at Hudson Lane
Improvements include but are not limited to retrofitting existing roadway lighting fixtures with LED luminaires, installation of new light poles.
Status: Construction is anticipated to finish in the summer of 2022